RE+ 2026 Recap: Power, Permitting, and M&A
Last updated:

The short answer: Speed to power was still the top theme at RE+ 2026 in Las Vegas, but the projects chasing it are getting smaller. Distributed data centers of 5 to 20 megawatts (MW), built for AI inference and often paired with behind-the-meter or bridge power, came up far more than last year. Two weeks before the show, voters restricted data centers in 40 of 41 local ballot measures, which pushed permitting and community risk to the front of site screening. With tax credit deadlines approaching and teams staying lean, developers have less room for sites that won’t make it, especially when they could have caught grid or permitting issues sooner.
I spent most of RE+ week speaking with developers, independent power producers (IPPs) and data center teams. The demand signal was the strongest I've heard. Interest in 1 to 15 MW projects has gone from close to zero to more than the market can supply in about six months, driven largely by mid-tier AI cloud providers that have chip allocations and need power by 2027. They will pay a premium for it. What changed is how much risk developers are willing to carry to get there.
What were developers talking about at RE+ 2026?
Speed to power, again. What's new is the scale: the conversation has moved from gigawatt campuses, to 100 to 300 MW sites, and now down to distributed compute at the distribution level.
- Bridge and behind-the-meter power. Anything that gets megawatts online sooner, grid-connected or not, is on the table. That can mean solar and battery energy storage (BESS) behind the meter on a large load site, or solar and storage serving as a bridge until a grid connection opens up around 2030. The engineers I talked to were more skeptical of gigawatt-scale onsite power. Their concerns were reliability, too little storage to handle harmonics, generation that can't ramp, and late design changes that strand equipment.
- Distributed compute. This wasn't a big topic last year. Now we hear about it constantly: edge data centers of 5 to 20 MW, built for inference rather than training, on existing industrial and renewable sites. The main barrier is education. It's a new kind of compute project with little precedent, so teams are still learning how to do it properly.
- Powered land and large load tariffs. Developers are shifting from standalone storage toward powered land, and some are hiring dedicated powered-land leads. Some new large load tariffs let utilities curtail big loads for set hours each year, so onsite backup is part of the plan from day one.
How did the 2026 midterm elections affect renewable and data center development?
The clearest signal for developers came from local ballots. On November 3, voters favored limits on data center development in 40 of 41 local ballot measures, according to Ballotpedia, including five full bans (in California, Florida and Ohio) and three six-month moratoriums, all in Maine.
The results didn't follow party lines. Political scientist Barbara Trish, in a piece Fortune republished, found the restrictions passed by an average margin of 49 points, in communities as different as Edgewater, Florida and Alhambra, California. A tracker we maintain holds about 1,200 local moratorium and ban records, and as of mid-October our permitting data flagged 239 jurisdictions with an active data center moratorium.
My personal read is that the results are net positive for renewables: with the incoming administration, there will likely be tailwinds for the industry rather than headwinds. That doesn't mean every proposal becomes law. A proposed moratorium doesn't necessarily become a moratorium, and in some cases stricter requirements for permits and grid connections are good for the industry. They force developers to think through how a project gets built in a way that benefits the community, and that affects how those sites are powered, renewables included.
The practical change for our customers: permitting and community risk now come up at the start of site screening, not at the end.
What macroeconomic forces are shaping power development right now?
Load growth. Even with more opposition to data centers, everything we hear says demand for compute isn't slowing, and it's pulling capital and people toward data center development.
- Talent is moving. Service providers are moving people from renewable developers to data center developers.
- Capital is moving up in scale. Investors who used to back only early and mid-stage development are now looking at utility-scale developers, whose capital needs keep growing.
- Tax credit deadlines are close. Under the One Big Beautiful Bill Act, wind and solar projects that didn't begin construction by July 4, 2026 must be placed in service by December 31, 2027 to claim the Section 45Y and 48E credits. Storage and other technologies have a longer runway, but many solar and wind projects are now racing the end-of-2027 deadline.
- Teams are leaner. Early in the data center boom, a lot of capital went to as many projects as possible to see which ones worked. Three or four years in, hyperscalers, neoclouds and energy developers are far more selective, pursuing the best opportunities with smaller teams as more of the manual work gets automated. One storage developer told us they want 70 sites under control by the end of 2027 with the team they have today.
Why do so few sites make it through development?
About 19% of projects that requested interconnection between 2000 and 2020 had reached commercial operation by the end of 2025, according to Lawrence Berkeley National Laboratory's Queued Up report. Many of the rest drop out late, on issues that were knowable early. Utility planning cases are out of date the day they're released, hosting capacity maps lag behind the grid, and early screens often skip permitting and interconnection checks.
The failure usually shows up months later. A team makes its modeling assumptions, submits an interconnection application, waits six to nine months for results, and learns there are 20 MW available where it assumed 200. Or a step in a conditional use permit application was missed early and surfaces at the end. On top of that, learning how much power a site can get often means multiple applications and large study fees to transmission owners.
The fix is to go to the source and keep the data fresh. When our development team builds a permit matrix, we check every public data source and then call the authority having jurisdiction (AHJ), whether that's a town, a county or a state agency. We join calls with utilities, planning boards and public utility commissions (PUCs). Those conversations also tell you how town hall meetings are going and how planning boards think about development. Once you have a direct line to those people, you have a much better sense of whether your project will get built.
How is M&A changing clean energy development?
Acquisitions are replacing some greenfield development. As larger projects face more community opposition and interconnection delays, many teams buy portfolios or single assets instead of starting from scratch, and they want answers quickly.
Buyers start with two questions. First, what does the seller have in the data room, and is it a real asset? Second, how fast can I get to a go or no-go decision? Another word we kept hearing at RE+ was velocity: buyers want gap and fatal-flaw analysis within the first five to ten days of a data room opening.
We also heard that smaller buyers feel underserved, with thin coverage and mostly automated output. They want senior, human-led diligence with automation behind it. Many buyers pay one vendor for early screening and another for full diligence and want to consolidate. Lenders want an independent second read of the data room to catch buried red flags before investment committee.
The best moment of the week at RE+
The most interesting booth I visited was Redwood Materials. Redwood gives lithium-ion batteries a second life, from electric vehicle packs down to laptop batteries, and its energy team deploys battery storage at scale using those second-life batteries. Paces has worked with Redwood for more than a year.
I walked up to their booth and recognized the project on display: a site our team found and helped develop, now built. Seeing a project go from a screening result to steel in the ground is the reason we do this work.
My take
AI compute is still driving most new energy demand. What's changing is the shape of it, from gigawatt-scale campuses toward smaller, distributed projects, and the bar for diligence that comes with it. The challenges around building data centers have downstream effects on renewable energy, but overall I came away from RE+ positive about where the industry is headed.
If you see it differently, reach out to me on LinkedIn. I'd like to hear what you're seeing.
Where does Paces fit?
Paces helps power developers quickly decide which projects to pursue. Here's how what we heard at RE+ maps to what we offer.
Every report is reviewed before it ships by people who have done this work: former developers, a dedicated risk team, and power engineers from Con Edison, NYISO and NYPA. Every dataset is timestamped and links to its source. Customers are also starting to connect AI assistants like Claude and ChatGPT to Paces data through our MCP beta to screen site lists and build site decks.
Bring us a site and get expert-vetted interconnection, permitting and land answers in days.